Status of Schemes Sanctioned for implementation under Untied Fund for the Year 2017-2018

  • Year wise Status of Schemes Sanctioned for  implementation under Untied Fund 
    SL NO Name of the Schemes Executing Agency Amount Sanctioned (Rs. In Lakhs) Amount Released (Rs. In Lakhs) Balance Amount (Rs. In Lakhs) Physical Progress Remarks
    1 Constn. Of Heliport ( Phase-II) at South Salmara, Tumni Construction Committee 50.00 37.50 12.50 80% APRs & UC yet to be received for relese of final installment
    2 Constn. Of Boundry Wall of S Ali HSS, Sukchar do 20.00 20.00 nil 100% Works Completed
    3 Constn. Of Addl Class Room 2 nos at Janata HSS, Kharubandha do 20.00 20.00 nil 100% Works Completed
    4 Constn. Of Latrine, Urinal and Water Supply facilities for utility at Sonapur Madrassa premises at Kathalbari do 10.00 10.00 nil 100% Works Completed